Environmental Resource Permitting

MCP Response Actions at Former Medfield State Hospital

Weston & Sampson was selected by the Massachusetts Department of Capital Asset Management and Maintenance (DCAMM) to comprehensively manage Massachusetts Contingency Plan (MCP) response actions for eight open Release Tracking Numbers (RTN) at the former Medfield State Hospital located in Medfield, Massachusetts.

One of these sites, known as the C&D area, was located adjacent to the Charles River.  In order to complete the remediation of the site, the project had to undergo full environmental permitting review.

In addition to delineating the site for Land under Water, Bank and Bordering Vegetated Wetland, this project was successfully permitted through the following environmental resource permitting process:

  • Wetlands Protection Act – NOI
  • MEPA Permitting – EENF
  • Section 401 Water Quality Certification
  • Chapter 91 Dredge Permit
  • ACOE General Permit Category II

BACK

Looking for assistance with your project?

Posted in Environmental Consulting, Permitting & Ecology and tagged , .