East Shore Lane to Maybank HP SI Gas Transmission Main Upsize (Phases I and II)
Weston & Sampson was instrumental in upsizing 6,500 LF of 6-inch high pressure steel gas transmission line to 8-inch to alleviate a "bottleneck" situation. The project was split into two phases that open cut and horizontal directional drill installation methods. Our firm performed a route survey and developed construction plans including plan and profile. Permits were acquired from SCDOT, DHEC OCRM, and Charleston County Zoning and Planning and MS4 Stormwater.