Transmission and Distribution Pipeline Relocation Project

12-inch transmission pressure steel pipeline

Utility Relocation Plans for NCDOT R-2507A/R-2583
Our firm provided utility conflict identification and relocation plans for NCDOT projects R-2507A/R-2583. We also provided transmission and distribution pipeline installation. These services were in support of NCDOT Roadway Improvement Project US 13/US 158 between Winton, North Carolina and Tarheel, North Carolina.

We developed a set of preliminary plans for the relocation of approximately four miles of 12-inch transmission pressure steel pipeline (R-2507A) and 1 mile of 6-inch distribution pipeline (R-2583). The pipelines were in conflict with proposed grading, drainage, and new pavement along the project corridor, as the existing highway was widened from two lanes to four. Re-location of the gas line consisted of a combination of open trench and horizontal directional drilling (HDD) methods to avoid wetland areas, lowland areas, and the interchange of US-13 and US-158. Work was performed on an accelerated schedule to comply with the Design Build Construction schedule.

BACK

Looking for assistance with your project?

Posted in Natural Gas, natural gas pipeline distribution, natural gas pipeline transmission and tagged , , , , .