Installation of Gas Distribution Main Pipeline

New Main Pipeline Installation with Survey, QA/QC, & Inspection

Weston & Sampson was selected for development of a gas distribution main installation to feed the new Pet Foods facility in Columbia, South Carolina.

The project consisted of five miles of 4-inch steel gas pipeline. Our team performed a route survey used to develop construction plans, including plan and profile. Permits were acquired from SCDOT, DHEC Stormwater, Saluda County MS4 Stormwater, and the Army COE.

Location
Columbia, SC
Categories
Distribution
Project Team
Chip Hutchens

Chip Hutchens

Regional Manager, North Carolina, Raleigh

Project Highlights

  • Gas Distribution Main Installation
  • Route Survey
  • Construction Plans
  • Permitting