Transmission & Distribution Pipeline Relocation

Pipeline Relocation to Resolve Utility Conflicts Along Corridor

Weston & Sampson provided utility conflict identification and relocation plans as well as transmission and distribution pipeline installation for projects in support of NCDOT Roadway Improvement Project US 13/US 158 between Winton, North Carolina and Tarheel, North Carolina

Our team developed a set of preliminary plans for the relocation of approximately four miles of 12-inch transmission pressure steel pipeline (R-2507A) and 1 mile of 6-inch distribution pipeline (R-2583). The pipelines were in conflict with proposed grading, drainage, and new pavement along the project corridor, as the existing highway was widened from two lanes to four. Relocation of the gas line consisted of a combination of open trench and Horizontal Directional Drilling (HDD) methods to avoid wetland areas, lowland areas, and the interchange of US-13 and US-158. Work was performed on an accelerated schedule to comply with the Design Build Construction schedule.

Location
Tarheel, NC
Categories
Transmission
Project Team
Chip Hutchens

Chip Hutchens

Regional Manager, North Carolina, Raleigh

Project Highlights

  • Utility Conflict Identification & Relocation Plans
  • Transmission & Distribution Pipeline Installation
  • Open Trench & Horizontal Directional Drilling (HDD)
  • Accelerated Schedule
  • Design Build Construction
  • 10-Inch Steel Transmission Line Installation
  • Installation of a Receiver & Associated Piping
  • Pipeline Interconnect Station Redesign & Relocation
  • Line Reconfigurations

Phase 2

The project included the installation of a new 10-inch steel transmission line between the new Wilmington Interconnect Station and the intersection of Line 9 and Line 9A; installation of a receiver and associated piping at the end of Line 9A, which will allow for internal inspection of Line 9A, Line 4, and new line 9L; redesign and relocation of the Wilmington Transmission Pipeline Interconnect Station from its current location at the Progress Energy Sutton Steam Power Plant; reconfiguration of Lines 4, 9 and E2 as part of the relocation of the Wilmington Interconnect Station.

Keep Exploring